SSEN network capacity map

Generation headroom, fault levels and the connection queue for Scottish and Southern Electricity Networks substations, taken from SSEN's open data and shown on one map with the other five GB distribution network operators. SSEN covers North Scotland, Central Southern England.

What SSEN publishes

3,291
Busbars at Primary and above
27%
With generation headroom
27%
With demand headroom
63%
With a fault level

Share of busbars carrying each figure in the current build. Full method on the data coverage page.

SSEN sites with the most queued generation

SiteQueuedConnectedProjects
Chickerell910 MW112 MW20
Nursling871 MW162 MW18
Mannington771 MW161 MW32
Coupar Angus720 MW119 MW22
Melksham706 MW137 MW14
Keith650 MW162 MW34
Abernethy628 MW147 MW26
Minety610 MW242 MW19
Elgin523 MW0 MW7
Kintore517 MW95 MW28

From the Embedded Capacity Register and the NESO TEC register. The full GB list is on the connection queue page.