ENW network capacity map
Generation headroom, fault levels and the connection queue for Electricity North West substations, taken from ENW's open data and shown on one map with the other five GB distribution network operators. ENW covers North West England.
What ENW publishes
36,063
Busbars at Primary and above
92%
With generation headroom
92%
With demand headroom
0%
With a fault level
Share of busbars carrying each figure in the current build. Full method on the data coverage page.
ENW sites with the most queued generation
| Site | Queued | Connected | Projects |
|---|---|---|---|
| Enw 609595 | 161 MW | 11 MW | 19 |
| Enw 238876 | 81 MW | 8.2 MW | 19 |
| Enw 459038 | 74 MW | 0.1 MW | 3 |
| Enw 200114 | 73 MW | 0.2 MW | 7 |
| Enw 609302 | 45 MW | 19 MW | 9 |
| Enw 616260 | 39 MW | 4.2 MW | 5 |
| Enw 666140 | 30 MW | 0.3 MW | 9 |
| Enw 609036 | 30 MW | 4.7 MW | 6 |
| Enw 609053 | 26 MW | 0.5 MW | 10 |
| Enw 644696 | 23 MW | 9.1 MW | 18 |
From the Embedded Capacity Register and the NESO TEC register. The full GB list is on the connection queue page.