Holme Upon Spalding Moor
PrimaryNPG33 kV 11 kV 6.6 kV
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
22
Projects
Planned Reinforcement
DNO Network Development Reports+13 MVA
Total uplift
2029
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Reinforcement of 1 x 66/11kV Txs, 66kV CB at Hayton, Cables and Fibre Wrap | Load | +12.8 MVA | 2029 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (3)
33kV
1 busbar11kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.