Elland
GSPNPGNGET275 kV 132 kV 33 kV +2 more
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
17
Projects
Planned Reinforcement
DNO Network Development Reports+64 MVA
Total uplift
2026
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of the Elland to Sowerby Bridge 1 and 2 132kV circuit | Asset replacement due to deteriorating condition | +63.5 MVA | 2026 |
Voltage Levels (9)
275kV
1 busbar132kV
1 busbar33kV
2 busbars11kV
2 busbarsELLAND 6 11 kVNPGunknown
distributionElland_NPg 11 kVNPG
distribution Gen Headroom
N/A
Demand Headroom
N/A
Fault Level (3ph)
N/A
Firm Capacity
N/A
6.6kV
1 busbarVoltage unspecified
2 busbarsData Source
Distribution Operator:Northern Powergrid
Transmission Owner:National Grid Electricity Transmission
Licence:NESO Open Data Licence
Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right [2019-]
Data sourced from publicly available DNO and TSO datasets. Indicative — verify directly with the operators before making connection decisions.