Elgar Road
PrimaryNPG33 kV 11 kV 6.6 kV
Network Hierarchy
CurrentElgar Road
BSPHull West
GSPCreyke Beck
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
1
Projects
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2026
First completion
3
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 33kV and 11kV switchgear | Condition | +0.0 MVA | 2026 |
| Replace the 33kV and 11kV switchgear | Asset replacement due to deteriorating condition and performance | — | 2026 |
| Replacement of 33kV Transformer T2 | Condition | +0.0 MVA | 2033 |
Voltage Levels (4)
33kV
1 busbar11kV
1 busbar6.6kV
1 busbarData Source
Primary DNO:Northern Powergrid
Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right [2019-]
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.