Dunston
Upstream:GSPStella North· headroom can be limited upstream
At a glance
Generation headroom, free
Green
Over 20MW
Source NPG Heat Map Data - Table (firm, demand, headroom), retrieved 27 Sep 2026Highest of 5 busbarsBand free, exact MW with Pro
Other figures
Sources retrieved 15 Oct 2026Highest figure across the site's 5 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Fault level near your switchgear rating? Star Delta Power does the study.
Location
Connection queue
NPG Embedded Capacity Register Part 2; NPG Embedded Capacity Register (>=1 MW), retrieved 15 Oct 2026
- Queued
- 0.0 MW
- Connected
- 1.5 MW
- Projects
- 5
66 kV
1 busbar20 kV
1 busbarDunston 20 kV
NPG Generation Lockeddistribution11 kV
1 busbarDunston 11 kV
NPG Generation LockeddistributionOther voltage levels
- 132 kVDunston 132 kV NPGNo capacity or fault data published for this busbar
- Voltage not statedDunston NPGNo capacity or fault data published for this busbar
Planned reinforcement
2 schemes, first in service 2027DNO Network Development Reports
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 20kV switchgear in a new switchroom | Condition | +0.0 MVA | 2027 |
| These works will impact upon the available capacity at this substation. | Asset replacement due to deteriorating condition and performance | 2027 |
Data source
Network operator: Northern Powergrid. Licence: Northern Powergrid Open Data Licence v1.0
Supported by Northern Powergrid Open Data Office for National Statistics licensed under the Open Government Licence v.3.0 Contains OS data © Crown copyright and database right [2019-]
Derived from publicly available DNO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the DNO before making connection decisions. Attribution and licences