Staygate
BSPNPG132 kV 33 kV
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
21
Projects
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2027
First completion
2
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 1.4km of 33kV underground cables | Condition | +0.0 MVA | 2027 |
| Replacement of 4.5km of 132kV overhead line | Condition | +0.0 MVA | 2033 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (2)
132kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.