Scartho
PrimaryNPG33 kV 11 kV
Network Hierarchy
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
12
Projects
Planned Reinforcement
DNO Network Development Reports+18 MVA
Total uplift
2033
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Full substation upgrade including transformers, 11kV switchboards and incoming circuits | Condition | +18.4 MVA | 2033 |
Voltage Levels (3)
33kV
1 busbar11kV
1 busbarData Source
Primary DNO:Northern Powergrid
Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right [2019-]
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.