Rodley
BSPNPG132 kV 33 kV
Network Hierarchy
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2033
First completion
2
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 22.3km of 132kV overhead line | Condition | +0.0 MVA | 2033 |
| Replacement of 22.3km of 132kV overhead line | Condition | +0.0 MVA | 2033 |
Voltage Levels (3)
132kV
1 busbar33kV
1 busbarData Source
Primary DNO:Northern Powergrid
Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right [2019-]
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.