Hull East
Upstream:GSPSaltend North· headroom can be limited upstream
At a glance
Generation headroom, free
Green
No headroom
Source NPG Heat Map Data - Table (firm, demand, headroom), retrieved 27 Sep 2026Highest of 4 busbarsBand free, exact MW with Pro
Other figures
Sources retrieved 15 Oct 2026Highest figure across the site's 4 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Fault level near your switchgear rating? Star Delta Power does the study.
Location
Connection queue
NPG Embedded Capacity Register (>=1 MW); NPG Embedded Capacity Register Part 2, retrieved 15 Oct 2026
- Queued
- 20 MW
- Connected
- 2.1 MW
- Projects
- 5
33 kV
1 busbar11 kV
1 busbarHULL EAST 11 kV
NPG Generation LockeddistributionOther voltage levels
- 132 kVHULL EAST 132 kV NPGNo capacity or fault data published for this busbar
- 6 kVHULL EAST 6 kV NPGNo capacity or fault data published for this busbar
Planned reinforcement
2 schemes, first in service 2027DNO Network Development Reports
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 11kV switchgear in a new switchroom. | Condition | +0.0 MVA | 2027 |
| Replacement of 132kV Grid Transformers | Condition | +0.0 MVA | 2027 |
Data source
Network operator: Northern Powergrid. Licence: Northern Powergrid Open Data Licence v1.0