Durkar Low Lane
PrimaryNPG33 kV 11 kV
Network Hierarchy
CurrentDurkar Low Lane
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2026
First completion
3
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 11kV switchgear in a new switchroom. | Condition | +0.0 MVA | 2026 |
| Replacement of 1.3km of 33kV overhead line | Condition | +0.0 MVA | 2033 |
| Replace 11kV switchgear in a new switchroom. | Asset replacement due to deteriorating condition and performance | — | — |
Voltage Levels (3)
33kV
1 busbar11kV
1 busbarData Source
Primary DNO:Northern Powergrid
Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right [2019-]
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.