Bramley
PrimaryNPG33 kV 11 kV 6.6 kV
Planned Reinforcement
DNO Network Development Reports+20 MVA
Total uplift
2033
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Full substation upgrade including transformers, switchboards and incoming circuits | Load | +19.9 MVA | 2033 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (3)
33kV
1 busbar11kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3