SOUTH BERSTED 11 kV
Network Hierarchy
CurrentSOUTH BERSTED 11 kV
GSPLOVEDEAN
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Install four new 33kV circuits between Shripney, Argyle Road and South Bersted to underground circuits (May 2025) Establish a new primary substation 'Chalcraft Lane' including 2 x 20/40MVA transformers to accommodate load growth in the South Bersted area (Apr 2031)
- There is no reverse power capacity at the BSB and new generations will requier new BSP Transformer, AVC reinfocement, 33kV switchgear reinforcement at Chichester BSP
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.