SLOUGH 33 kV
BSPSSEN33 kV
Network Hierarchy
CurrentSLOUGH 33 kV
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Gen: Upstream Fault Level Constraint
- Demand: Substation Thermal Capacity & Upstream Thermal Capacity
- Install a 3rd 90MVA transfrormer
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.