HASLINGBOURNE 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentHASLINGBOURNE 11 kV
BSPALTON & FERNHURST
GSPFLEET BRAMLEY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Alton & Fernhurst BSP group to be split (Sept 2025) Replace the AIS switchboad at Alton with a GIS switchboard (Jun 2028) A new 132kV switching station is to be established between Fleet GSP, Alton BSP and Fernhurst BSP to supply Alton and Fernhurst from Nursling under N-2 conditions (Aug 2028) Fleet & Bramley GSP group to be split and a new 132kV switchboard installed at Bramley (Jul 2030)
- Limited flexible headroom on the 132 kV circuits from Fleet. Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV fault level reinforcement required at Fleet GSP. Voltage issues. Fault level reinforcement required at Fernhurst 33 kV
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.