Haslingborne Primary

PrimarySSEN11 kV

Location

Loading map...
Coordinates

50.973539, -0.602886

From DNO data
Get Directions

Network Hierarchy

CurrentHaslingborne Primary
BSPFernhurst BSP

Headroom may be constrained by upstream infrastructure (BSP/GSP)

Generation Headroom

██.█MW

Demand Headroom

██.█MW

Fault Levels

3-Phase Fault

██.█kA

1-Phase Fault

██.█kA

Ratings

Make Rating
Not in DNO data
Break Rating

██.█kA

Firm Capacity

██.█MVA

Network Constraints

Constraint Details
  • Gen: Upstream Thermal Capacity
  • Replace both transformers with 12 / 24MVA units
Upstream TX Queue N/A
contracted generationat upstream GSP

High queue indicates significant generation already contracted at this connection point.

Data Source

DNO:Scottish and Southern Electricity Networks
License:OGL v3

Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.