BEACONSFIELD (END B/B)
PrimarySSEN6.6 kV
Network Hierarchy
CurrentBEACONSFIELD (END B/B)
BSPUPTON
GSPIVER 132KV
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Upgrade of 3 275/132kV SGTs required as per current Modification Application. Modification Application in progress to assess capacity at Iver 132kV Install 2 new 33kV circuits from Loudwater GSP feeding a new 2 x 40MVA 33/11/6.6kV substation rationalising the existing Beaconsfield End / Beaconsfield Middle substation layout (March 2029)
- Moderate proximity to Primary transformers limitations under FCO.
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.