Seaton Burn
PrimaryNPG66 kV 20 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2026
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replace the 66 & 20kV switchgear | Asset replacement due to deteriorating condition and performance | — | 2026 |
Voltage Levels (3)
66kV
1 busbar20kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.