Seabank
Upstream:GSPIron Acton· headroom can be limited upstream
At a glance
Generation headroom, free
Red
5 to 20MW
Source NGED LTDS Capacity Heatmap, four licence areas (July 2026), retrieved 27 Sep 2026Highest of 2 busbarsBand free, exact MW with Pro
Other figures
Sources retrieved 17 Oct 2026Highest figure across the site's 2 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Fault level near your switchgear rating? Star Delta Power does the study.
Location
Connection queue
NESO TEC Register (live, archive datastore dump), retrieved 17 Oct 2026
- Queued
- 50 MW
- Connected
- 1.2 GW
- Projects
- 2
33 kV
1 busbarOther voltage levels
- Voltage not statedSeabank NGETNot openly published by NESO
Data source
Distribution operator: National Grid Electricity Distribution. Licence: WPD Open Data Licence
Transmission owner: National Grid Electricity Transmission. Licence: NESO Open Data Licence
Supported by NGED Open Data Supported by National Energy SO Open Data
Derived from publicly available DNO and TSO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the operators before making connection decisions. Attribution and licences