Rookery Lane 33 kV
NGEDdistributionNot published for this busbar: generation headroom, demand headroom, firm capacity.
Upstream:GSPWest Burton· headroom can be limited upstream
Generation headroom, free
Green
5 to 20MW
Source NGED LTDS Capacity Heatmap, four licence areas (July 2026), retrieved 27 Sep 2026Highest of 2 busbarsBand free, exact MW with Pro
Other figures
Sources retrieved 27 Sep 2026Highest figure across the site's 2 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Fault level near your switchgear rating? Star Delta Power does the study.
Network operator: National Grid Electricity Distribution. Licence: WPD Open Data Licence
Supported by NGED Open Data
Derived from publicly available DNO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the DNO before making connection decisions. Attribution and licences