Melksham 132 kV
NGEDdistributionNot published for this busbar: generation headroom, demand headroom, firm capacity.
Highest figure across the site's 2 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
NGED connection queue, 45 per-GSP CSVs, one row per machine; NESO TEC Register (live, archive datastore dump), retrieved 7 Oct 2026
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Change 2 x 132kV circuit breakers | Fault Level capability | 2026 |
Distribution operator: National Grid Electricity Distribution. Licence: WPD Open Data Licence
Transmission owner: National Grid Electricity Transmission. Licence: NESO Open Data Licence
Supported by NGED Open Data Supported by National Energy SO Open Data
Derived from publicly available DNO and TSO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the operators before making connection decisions. Attribution and licences