LYNDHURST 33 kV
SSEN Generation LockeddistributionNot published for this busbar: generation headroom, demand headroom, firm capacity.
Generation headroom, free
Red
No headroom
Source SSEN Headroom Dashboard Data, March 2026, retrieved 27 Sep 2026Highest of 3 busbarsBand free, exact MW with Pro
Other figures
Sources retrieved 14 Oct 2026Highest figure across the site's 3 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Fault level near your switchgear rating? Star Delta Power does the study.
SSEN ECR Part 1, 1 MW and 50 kW registers (files), retrieved 14 Oct 2026
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Demand reinforcement at Lyndhurst (NSHR expected in-service date 2032) | Capacity | 2032 | |
| Generation reinforcement at Lyndhurst (NSHR expected in-service date 2035) | Capacity | 2035 |
Distribution operator: Scottish and Southern Electricity Networks. Licence: CC BY 4.0
Transmission owner: Scottish and Southern Electricity Networks Transmission. Licence: CC BY 4.0
SSEN Transmission is a trading name of Scottish Hydro Electric Transmission plc, company number SC213461
Derived from publicly available DNO and TSO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the operators before making connection decisions. Attribution and licences