Hemsworth
PrimaryNPG66 kV 11 kV
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
5
Projects
Planned Reinforcement
DNO Network Development Reports+15 MVA
Total uplift
2033
First completion
1
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| New Transformer to be added and shared with South Kirkby | Load | +15.0 MVA | 2033 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (2)
66kV
1 busbarData Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.