Doncaster B Thorpe Marsh
Upstream:GSPWest Melton / Thorpe Marsh· headroom can be limited upstream
At a glance
Generation Locked Sources retrieved 27 Sep 2026- Generation headroom
- ██.█MW
- Doncaster B/Thorpe Marsh. NPG Heat Map Data - Table (firm, demand, headroom), retrieved 27 Sep 2026
Highest figure across the site's 2 busbars; fault level is the busbar nearest its break rating. Each busbar is listed below.
Location
Connection queue
NPG Embedded Capacity Register Part 2; NPG Embedded Capacity Register (>=1 MW), retrieved 27 Sep 2026
- Projects
- 12
66 kV
1 busbarOther voltage levels
- Voltage not statedDoncaster B/Thorpe Marsh NPGNo capacity or fault data published for this busbar
Planned reinforcement
2 schemes, first in service 2030DNO Network Development Reports
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 66kV switchgear | Connections | +0.0 MVA | 2030 |
| Replacement of 12.1km of 66kV overhead line | Condition | +0.0 MVA | 2033 |
Data source
Network operator: Northern Powergrid. Licence: Northern Powergrid Open Data Licence v1.0
Supported by Northern Powergrid Open Data Office for National Statistics licensed under the Open Government Licence v.3.0 Contains OS data © Crown copyright and database right [2019-]
Derived from publicly available DNO datasets: we cluster, merge and calculate from the published records, so these figures are modified from the source. Indicative only; verify directly with the DNO before making connection decisions. Attribution and licences