SELLINDGE 132 KV
GridUKPN132 kV
Network Hierarchy
CurrentSELLINDGE 132 KV
BSPSouth Eastern Power Networks (SPN)
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Generation Headroom
Not in DNO data
Demand Headroom
Not in DNO data
Network Constraints
Constraint Details
- Site classified HOT (high earth potential rise)
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.