BETTESHANGER GRID 132 KV
GridUKPN132 kV
Network Hierarchy
CurrentBETTESHANGER GRID 132 KV
BSPSouth Eastern Power Networks (SPN)
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Generation Headroom
Not in DNO data
Demand Headroom
Not in DNO data
Network Constraints
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.