WROUGHTON 11 kV
Network Constraints
Constraint Details
- Upstream constrained
- Establish a new 132kV switchboard, replace and debank the existing 45MVA BSP transformers with 90MVA units (Mar 2027) Install 2 new 33kV circuits between Toothill BSP and Wroughton (Mar 2025)
- thermal constraint on Minety - Galileo 132kV cct
- Upstream queue: 380.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.