WITNEY TOWN 11 kV
Network Constraints
Constraint Details
- Upstream constrained
- Reinforce 2 x 132kV circuits between Witney and Yarnton BSP's and add a 3rd 90MVA transformer
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.