WINTERBORNE KINGSTON
Network Hierarchy
CurrentWINTERBORNE KINGSTON
BSPLYTCHETT
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Replace both the 33kV switchboard and the existing transformers with 120MVA units
- BSP Transformer rating under N-1
- Upstream queue: 95.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.