WHITCHURCH 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentWHITCHURCH 11 kV
BSPANDOVER
GSPMELKSHAM
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Subject to Mod App outcome Replace the 132kV switchgear and install a 3rd 90MVA BSP transformer at Andover (Dec 2026) Add a new 33kV circuit between Barton Stacey and Whitchurch primaries (Jun 2028)
- Thermal constraint on upstream 132kV system with no headroom. National Grid reinforcement works required for Melk SGT capacity constraints, est connection date for new applications is 2025-2027.
- Upstream queue: 515.5MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.