WHEATLEY 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentWHEATLEY 11 kV
BSPHEADINGTON
GSPCOWLEY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Reinforce the existing 33kV circuits between Headington and Wheatley Remove Headington from the existing Headington - Yarnton - Witney 132kV circuit via 2 new 132kV circuits run directly from Cowley GSP (Aug 2026)
- Limited space for extension.
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.