WEYMOUTH 11 kV
Network Hierarchy
Network Constraints
Constraint Details
- Upstream constrained
- Reinforcement is triggered to take Redlands PSS off the meshed 33kV networks (Jun 2026) Add a 3rd 90MVA BSP transformer at Chickerell (Dec 2026)
- There is no reverse power capacity at the Chickerell BSP
- Upstream queue: 800.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.