TEMPLE FARM 11 kV
Network Hierarchy
CurrentTEMPLE FARM 11 kV
BSPMAIDENHEAD
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Fleet & Bramley GSP group to be split and a new 132kV switchboard installed at Bramley (Jul 2030)
- Voltage issues with the 33kV upstream network Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV reinforcement required at Fleet GSP Constrained on the 132kV circuits for export
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.