PLESSEY
Network Hierarchy
Network Constraints
Constraint Details
- Upstream constrained
- Replace the 33kV switchboard and establish an auto-close scheme to run Stratton solid under N-1 of losing a 132/33kV transformer
- Upstream queue: 380.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.