MILFORD-ON-SEA 11 kV
Network Hierarchy
CurrentMILFORD-ON-SEA 11 kV
BSPARNEWOOD
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Replace the 132kV and 33kV switchgear alongside the addition of a 3rd 60MVA BSP transformer at Arnewood (Jun 2028) Remove Christchurch BSP from the existing Arnewood - Christchurch - Redhill 132kV network via 2 new 132kV direct circuits between Mannington GSP and Christchurch (Sep 2029)
- No spare bay.
- Upstream queue: 95.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.