MALMESBURY 11 kV
Network Hierarchy
CurrentMALMESBURY 11 kV
BSPCHIPPENHAM
GSPMELKSHAM
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Subject to Mod App outcome Replace the 33kV switchgear at Chippenham BSP (Aug 2027) Reinforce the 132kV circuits between Melksham GSP and Chippenham (Aug 2027) Reinforce the 33kV circuit between Malmesbury and Tetbury (Mar 2028) Add a 3rd 90MVA BSP transformer at Chippenham (Oct 2027)
- Constrained due to upstream thermal limitations on Chippenham BSP TX under N-1 plus local voltage constraint.
- Upstream queue: 515.5MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.