GUSSAGE ST MICHAEL 11 kV
Network Hierarchy
CurrentGUSSAGE ST MICHAEL 11 kV
BSPSHAFTESBURY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Add a dual 132kV circuit between Mannington GSP and Shaftesbury BSP (Mar 2030)
- Constrained due to Primary transformers limitations under FCO.
- Upstream queue: 95.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.