GODALMING 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentGODALMING 11 kV
BSPALDERSHOT
GSPFLEET BRAMLEY
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Fleet & Bramley GSP group to be split and a new 132kV switchboard installed at Bramley (Jul 2030)
- Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV reinf required at Fleet GSP. Fleet GSP 132kV switchgear saturated for fault level capacity. 132kV reinf required at Fleet GSP
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.