DORCHESTER
Network Hierarchy
Network Constraints
Constraint Details
- Upstream constrained
- Reinforce 33kV feeder circuits to match the Primary transformer ratings (Jul 2025) Reinforcement is triggered to take Redlands PSS off the meshed 33kV networks (Jun 2026) Add a 3rd 90MVA BSP transformer at Chickerell (Dec 2026)
- Upstream 33kV circts restrictions under FCO. Potential Voltage issue for new connections.There is no reverse power capacity at the Chickerell BSP
- Upstream queue: 800.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.