CHILTON CANTELO
Network Constraints
Constraint Details
- Upstream constrained
- Replace Axminster to Yeovil oil filled cable circuit 2 (Jun 2028) Install a new 3132kV circuit between Axminster GSP and Yeovil BSP and replace both 60MVA transformers with 90MVA units (Feb 2031)
- Distribution constrained
- Moderate proximity to upstream 33kV circts restrictions.There is no reverse power capacity at the Yeovil BSP,33kV circuit thermal limitation.
- Upstream queue: 120.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.