BRIDGE ROAD 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentBRIDGE ROAD 11 kV
GSPEaling GSP
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Gen: Substation Fault Level & Upstream Fault Level Constraint
- Replace the existing transformers with 80MVA units
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.