BLEDINGTON
Network Constraints
Constraint Details
- Upstream constrained
- Reinforce 2 x 132kV circuits between Witney and Yarnton BSP's and add a 3rd 90MVA transformer
- Moderate proximity to Primary transformers limitations under FCO.
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source