BILLINGSHURST 11 kV
PrimarySSEN11 kV
Network Hierarchy
CurrentBILLINGSHURST 11 kV
BSPCHICHESTER & HUNSTON
GSPLOVEDEAN
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- No capacity due to 11kV backfeed limitation.
- There is no reverse power capacity at the BSP and new generations will require new BSP Transformer, AVC reinforcement, 33kV switchgear reinforcement at Chichester BSP
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.