BEVOIS VALLEY 6.6 kV
PrimarySSEN6.6 kV
Network Hierarchy
CurrentBEVOIS VALLEY 6.6 kV
BSPSouthampton (2 x 60)
GSPNURSLING
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Network Constraints
Constraint Details
- Upstream constrained
- Replace the existing Southampton Main / Reserve arrangement with a new BSP. This will require 2 new 132kV circuits to be run from Nursling GSP to the new BSP, replacement of the existing BSP transformers with 3 x 90MVA units and a new 33kV switchboard
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.