BEMERTON 11 kV
Network Hierarchy
Network Constraints
Constraint Details
- Upstream constrained
- There is thermal restriction at MANN-SALI 132kV cct completion TBC Remove Bemerton Primary from the existing 33kV ring network via 2 new 33kV circuits (Jun 2029) Remove Petersfinger Primary from the existing 33kV ring network via 2 new 33kV circuits (Jun 2029)
- Constrained due to upstream thermal limitations.
- Upstream queue: 95.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:Scottish and Southern Electricity Networks
License:OGL v3
Data sourced from publicly available DNO datasets. This data is indicative and should be verified directly with the DNO before making connection decisions.