BEENHAM 11 kV

PrimarySSEN11 kV

Location

Loading map...
Coordinates

51.417262, -1.164401

From DNO data
Get Directions

Network Hierarchy

CurrentBEENHAM 11 kV
BSPTHATCHAM
GSPBRAMLEY (ANDO-THAT)

Headroom may be constrained by upstream infrastructure (BSP/GSP)

Generation Headroom

██.█MW

Demand Headroom

██.█MW

Fault Levels

3-Phase Fault

██.█kA

1-Phase Fault

██.█kA

Ratings

Make Rating
Not in DNO data
Break Rating

██.█kA

Firm Capacity

██.█MVA

Network Constraints

Constraint Details
  • Upstream constrained
  • Install a new 132kV circuit between Ashford Hill and Thatcham to maintain security of supply (Jul 2028) Install a new 90MVA BSP transformer at Thatcham (Oct 2028) Install a new 132kV circuit between Bramley and Thatcham (Dec 2031) Reinforce the Thatcham to Beenham 33kV circuit and modify the protection at Thatcham (Jan 2031)
  • Fault level reinforcement required at Thatcham 33kV. Approaching 100% loading on 132kV circuits from Bramley to Thatcham on import
  • Upstream queue: 537.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP

High queue indicates significant generation already contracted at this connection point.

Data Source

DNO:Scottish and Southern Electricity Networks
License:OGL v3