Feeder Road 132 kV
NGED132 kV
Network Hierarchy
CurrentFeeder Road 132 kV
Headroom may be constrained by upstream infrastructure (BSP/GSP)
Generation Headroom
Not in DNO data
Demand Headroom
Not in DNO data
Network Constraints
Constraint Details
- Upstream queue: 120.0MW
Upstream TX Queue N/A
contracted generationat upstream GSP
High queue indicates significant generation already contracted at this connection point.
Nearby Substations
Data Source
DNO:National Grid Electricity Distribution
License:OGL v3