Stonehouse
SecondarySPEN11 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2025
First completion
2
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| New 11kV interconnector between Stonehouse and Strathaven primary substations. | Reinforcement | — | 2025 |
| Utilise a section of de-energised 33kV overhead line (OHL), to form part of a new interconnected 11kV circuit to Strathaven Primary, that would otherwise be decommissioned. Establish a HV automated load transfer scheme to adjacent primaries under N-1. | Thermal capacity | — | 2026 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (1)
Data Source
Primary DNO:SP Energy Networks
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.