Starbeck
UnknownNPG
Generation Connection Queue
Embedded Capacity Register + NESO TEC██ MW
Queued
██ MW
Connected
3
Projects
Planned Reinforcement
DNO Network Development Reports+25 MVA
Total uplift
2026
First completion
3
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replacement of 9.1km of 33kV underground cables | Condition | +0.0 MVA | 2026 |
| Full rebuild of substation, two transformers & Circuit breakers | Load | +22.8 MVA | 2029 |
| Flexibility | Load | +2.5 MVA | 2029 |
Voltage Levels (2)
Data Source
Primary DNO:Northern Powergrid
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.