Levenbank
SecondarySPEN11 kV
Planned Reinforcement
DNO Network Development Reports—
Total uplift
2025
First completion
2
Schemes
| Scheme | Driver | Uplift | In service |
|---|---|---|---|
| Replace 2x 10MVA primary transformers with 20MVA units. | Reinforcement | — | 2025 |
| Replace the existing 10MVA 33/11kV transformers at Levenbank Primary with new 20MVA units. | Thermal capacity | — | 2027 |
Capacity Forecast
Premium Unlock multi-year capacity forecasts with premium
Voltage Levels (1)
Data Source
Primary DNO:SP Energy Networks
License:OGL v3
Data sourced from publicly available DNO datasets. Indicative — verify directly with the DNO before making connection decisions.